Well the under floor part of the great house DIY of ‘07 is done.
In the process we have:
- moved 2,500 kg’s of dirt and rubble from under the house
- laid 100m2 of polythene ground sheeting
- used 180m of tape
- got a lot of sore muscles from crawling around in 30cm’s of space for days on end
But the floor looks good
Now on with:
- laying the floor back down
- replacing some wall studs
- putting weatherboards back on outside of house
and it will be done!